Roads23I00142

CONCRETING OF BRGY. CARNAGA TO BRGY. MANLICO FMR, BRGY. CARNAGA AND BRGY. MANLICO, SAINT BERNARD, SOUTHERN LEYTE

CONCRETING OF BRGY. CARNAGA TO BRGY. MANLICO FMR, BRGY. CARNAGA AND BRGY. MANLICO, SAINT BERNARD, SOUTHERN LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱11,939,760.98. Status: Reported complete (DPWH). Contractor on record: BUILD SMART CONST AND DEVELOPMENT CORP. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

32 projects · ₱200.1M total · 0 flags

Other projects by this contractor

View all 32 projects →

4. Implementation

Contract Amount

₱11,939,760.98

Progress

Reported complete (DPWH)

Start Date

October 11, 2023

Target End

August 28, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.