Construction of Flood Mitigation Structure21FA0038

Construction/Extension of Soa River Control (Upstream Right Side), Malinao, Albay

Construction/Extension of Soa River Control (Upstream Right Side), Malinao, Albay is a DPWH-tracked public work in ALBAY, Region V. Reported contract value: ₱9,900,000.00. Status: Reported complete (DPWH). Contractor on record: JORMAND CONST & SUPPLY. Figures trace to sumbong.

ALBAY, Region V
Region: Region V

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱13,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Extension of the Flood Mitigation/River Control at the Panarayon River (Downstream, Right side) in Bacacay, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0007579

₱14,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0014172

₱10,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010291

₱5,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0011457

₱4,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,900,000.00

Progress

Reported complete (DPWH)

Start Date

April 19, 2022

Target End

September 15, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.