Bridges24PK0057

BIP - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF GALGALIS - PALANGHA FALLS - MABILONG BRIDGE, BARANGAY LUPLUPA, BARANGAY TULGAO, BARANGAY MABILONG, TINGLAYAN AND LUBUAGAN, KALINGA

BIP - INTERJURISDICTIONAL ROADS AND/OR BRIDGES (OR, ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF GALGALIS - PALANGHA FALLS - MABILONG BRIDGE, BARANGAY LUPLUPA, BARANGAY TULGAO, BARANGAY MABILONG, TINGLAYAN AND LUBUAGAN, KALINGA is a DPWH-tracked public work in Upper Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱4,944,970.75. Status: Reported complete (DPWH). Contractor on record: MIGHTY STELLAR DEVELOPMENT CONST. Figures trace to dpwh.

Upper Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱7,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Saltan, Biyog Creek, Batong Buhay NHS, Mataliling Kiloy, Mabilong in Barangay Balbalasang, Barangay Balatoc, Barangay Upper Uma, Barangay Mabilong, Balbalan, Pasil and Lubuagan, Kalinga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Upper Kalinga DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

6 projects · ₱26.0M total · 0 flags

Other projects by this contractor

No sat.

FARM-TO-MARKET ROAD (FMR) PROJECTS CONCRETING OF BRGY. BELONG TO BRGY. DANANAO FMR, BRGY. BELONG AND BRGY. DANANAO, TINGLAYAN, KALINGA.

Upper Kalinga DEO, Cordillera Administrative Region

2024₱9.8M
Reported complete (100% progress, DPWH status On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOOD: FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS: CONSTRUCTION OF FLOOD CONTROL STRUCTURE, BUGNAY (PHASE 2), TINGLAYAN, KALI

Upper Kalinga DEO, Cordillera Administrative Region

2025₱4.9M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BIP - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF LIWAN WEST MULTI-PURPOSE BUILDING, RIZAL, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2024₱2.5M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY ROMUALDEZ, RIZAL, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2023₱2.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING, BARANGAY LIWAN WEST, RIZAL, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2023₱1.9M
Reported complete (DPWH)
View all 6 projects →

4. Implementation

Contract Amount

₱4,944,970.75

Progress

Reported complete (DPWH)

Start Date

June 13, 2024

Target End

August 26, 2024

5. Audit