Flood Control and Drainage24G00005

CONSTRUCTION OF REVETMENT WALL ALONG TANGALAN RIVER, TANGALAN, AKLAN

CONSTRUCTION OF REVETMENT WALL ALONG TANGALAN RIVER, TANGALAN, AKLAN is a DPWH-tracked public work in Region VI, Region VI. Reported contract value: ₱147,403,750.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: IBC INTERNATIONAL BUILDERS CORP. Figures trace to dpwh.

Region VI, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2024 GAA. DBM GAA FY2024

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱147,403,750.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

February 8, 2024

Target End

January 16, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.