Roads24M00323

ROAD CONCRETING FROM BARANGAY MUTI TO BARANGAY AHAN, GUINDULUNGAN, MAGUINDANAO DEL SUR (1KM), STA. 0+000.00 - STA. 0+600.00, GUINDULUNGAN, MAGUINDANAO DEL SUR

ROAD CONCRETING FROM BARANGAY MUTI TO BARANGAY AHAN, GUINDULUNGAN, MAGUINDANAO DEL SUR (1KM), STA. 0+000.00 - STA. 0+600.00, GUINDULUNGAN, MAGUINDANAO DEL SUR is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱9,628,607.07. Status: Past target date (DPWH On-Going). Contractor on record: KLD ENGINEERING CONST 40577. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Money Trail

1. Appropriation

No GAA appropriation line matched for this project at current confidence thresholds.

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,628,607.07

Progress

Past target date (DPWH On-Going)

Start Date

July 4, 2025

Target End

August 25, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.