Buildings and Facilities18PA0056

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE II, BRGY. TANGADAN, SAN QUINTIN, ABRA

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE II, BRGY. TANGADAN, SAN QUINTIN, ABRA is a DPWH-tracked public work in Abra DEO, Cordillera Administrative Region. Reported contract value: ₱4,750,445.57. Status: Reported complete (DPWH). Contractor on record: A D MARRERO GEN CONST. Figures trace to dpwh.

Abra DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱48,982,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Abra River, Sta. 0+000 - 0+968, San Miguel-Pagala, Bucay, Abra
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-B-18-0008433

₱20,462.00 · FY2018

Released to Regional Office - I (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱4,750,445.57

Progress

Reported complete (DPWH)

Start Date

February 2, 2018

Target End

July 31, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.