Roads23FM0027

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - POBLACION-MOROCBOROCAN-GUINHADAP ROAD, MASBATE.

NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - POBLACION-MOROCBOROCAN-GUINHADAP ROAD, MASBATE. is a DPWH-tracked public work in Masbate 1st DEO, Region V. Reported contract value: ₱34,299,971.09. Status: Reported complete (DPWH). Contractor on record: NEXT GENERATION CONST AND SUPPLY CORP. Figures trace to dpwh.

Masbate 1st DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱24,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure (Upstream), Brgy. Progreso, San Fernando, Masbate
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Masbate 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

218 projects · ₱6.6B total · 1 flags

4. Implementation

Contract Amount

₱34,299,971.09

Progress

Reported complete (DPWH)

Start Date

April 11, 2023

Target End

December 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.