Flood Control and Drainage18CK0016

REHAB/IMPT OF EXISTING DIKE ALONG PARUA RIVER (RIGHT BANK), U/S OF STA. RITA BRIDGE, CONCEPCION, TAR

REHAB/IMPT OF EXISTING DIKE ALONG PARUA RIVER (RIGHT BANK), U/S OF STA. RITA BRIDGE, CONCEPCION, TAR is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱22,573,567.65. Status: Reported complete (DPWH). Contractor on record: GVDPM CONST CORP FORMERLY: ZM CONSTRUCTIO. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱24,250,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Existing Dike along Parua River, Sta. 11+110 to Sta. 11+238 and Sta. 11+473 to Sta. 11+650 , (Right Bank), U/S of Sta. Rita Bridge, Concepcion, Tarlac
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0029562

₱0.00 · FY2018

Released to Division of Tarlac (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

166 projects · ₱9.9B total · 2 flags

4. Implementation

Contract Amount

₱22,573,567.65

Progress

Reported complete (DPWH)

Start Date

February 15, 2018

Target End

June 28, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.