GAA 2023 OO-123KC0043

ROAD WIDENING ALONG SAYRE HIGHWAY - K1443+160-K1443+940, MANOLO FORTICH, BUKIDNON

ROAD WIDENING ALONG SAYRE HIGHWAY - K1443+160-K1443+940, MANOLO FORTICH, BUKIDNON is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱67,791,836.73. Status: Reported complete (DPWH). Contractor on record: ED1SON DEVELOPMENT. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱10,355,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Misamis Oriental-Bukidnon-Agusan Road (Downstream) of Siloo Bridge with slope protection, Malitbog, Bukidnon
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bukidnon 3rd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

351 projects · ₱8.3B total · 0 flags

4. Implementation

Contract Amount

₱67,791,836.73

Progress

Reported complete (DPWH)

Start Date

July 10, 2023

Target End

July 17, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.