Construction of Flood Mitigation Structure24E00163

Construction of Road Dike along Mag-asawang Tubig River, Barangay Pinagsabangan 2 - Barangay Motoderazo, Naujan, Oriental MIndoro

Construction of Road Dike along Mag-asawang Tubig River, Barangay Pinagsabangan 2 - Barangay Motoderazo, Naujan, Oriental MIndoro is a DPWH-tracked public work in NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B. Reported contract value: ₱48,247,759.16. Status: Reported complete (DPWH). Contractor on record: MLR SOLID CONST AND DEVELOPMENT CORP. Figures trace to sumbong.

NAUJAN (ORIENTAL MINDORO), ORIENTAL MINDORO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation along Bucayao River Sitio Barucan, Brgy. San Luis, Naujan, Oriental Mindoro
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008378

₱1,267,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004239

₱1,035,174.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0001426

₱2,931,832.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0008390

₱117,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0004240

₱92,822.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-24-0001427

₱270,752.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱48,247,759.16

Progress

Reported complete (DPWH)

Start Date

March 2, 2024

Target End

July 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.