Bridges24IM0007

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - KAWAYAN BR. (B00022LT) ALONG LEYTE-SAMAR RD (VIA GUINTIGUI-AN)

RETROFITTING/STRENGTHENING OF PERMANENT BRIDGES - KAWAYAN BR. (B00022LT) ALONG LEYTE-SAMAR RD (VIA GUINTIGUI-AN) is a DPWH-tracked public work in Tacloban City DEO, Region VIII. Reported contract value: ₱6,337,616.93. Status: Reported complete (DPWH). Contractor on record: ZTATIK BUILDER INC. Figures trace to dpwh.

Tacloban City DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure and Water Catchment Structure, along Salvacion, Tigbao, Tacloban City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Tacloban City DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱6,337,616.93

Progress

Reported complete (DPWH)

Start Date

January 29, 2024

Target End

April 27, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.