Buildings and Facilities23ID0126

CONSTRUCTION OF SUPER RHU MAC ARTHUR PRIMARY CARE FACILITY,MAC ARTHUR,LEYTE

CONSTRUCTION OF SUPER RHU MAC ARTHUR PRIMARY CARE FACILITY,MAC ARTHUR,LEYTE is a DPWH-tracked public work in Leyte 2nd DEO, Region VIII. Reported contract value: ₱24,741,634.06. Status: Past target date (DPWH On-Going). Contractor on record: KML BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Leyte 2nd DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Tunga River, Brgy. Astorga, Tunga, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Leyte 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱24,741,634.06

Progress

Past target date (DPWH On-Going)

Start Date

September 18, 2024

Target End

July 28, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.