Buildings and Facilities15PD0043

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION AND EXTENSION THE BARANGAY MULTI-PURPOSE HALL, LOPEZ JAENA, BAGUIO CITY LONE DISTRICT

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION AND EXTENSION THE BARANGAY MULTI-PURPOSE HALL, LOPEZ JAENA, BAGUIO CITY LONE DISTRICT is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱1,869,833.95. Status: Reported complete (DPWH). Contractor on record: SEGAL CONST. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control (Slope Protection) at Brookside, Baguio City Lone District
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVI-16-0011713

₱60,921,463.00 · FY2016

Released to Western Visayas Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

14 projects · ₱28.8M total · 0 flags

Other projects by this contractor

No sat.

LOCAL INFRASTRUCTURE PROGRAM-CONST OF MPB, BAGUIO CITY, BENGUET: A) CONST. OF MPB SAN ANTONIO AURORA HILL, BAGUIO CITY B) CONST. OF MPB , WEST BAYAN, LEONILA HILL, BAGUIO CITY

Baguio City DEO, Cordillera Administrative Region

2017₱4.4M
Reported complete (DPWH)
No sat.

CONTRACT PACKAGE 22: DRERF - FLOOD CONTROL AND DRAINAGE -DRAINAGE/PROTECTION WORKS: RESTORATION OF DAMAGE SLOPE PROTECTION DAMAGED BY TYPHOON OMPONG A) REVETMENT WALL ALONG BUED RIVER (F40033LZ) B) RESTORATION OF COLLAPSED REVETMENT WALL ALONG LOAKAN BR.1

Baguio City DEO, Cordillera Administrative Region

2018₱3.0M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION OF NATIONAL ROADS- CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-TERTIARY:CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - QUEZON HILL RD. # 1, KO308+780-KO309+110

Baguio City DEO, Cordillera Administrative Region

2017₱2.6M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM-OPENING AND CONCRETING OF ROAD BETWEEN BLOCK 1 AND 4 TAPAO PORTION OF THE BARANGAY, MIDDLE QUIRINO HILL, BAGUIO CITY, BENGUET

Baguio City DEO, Cordillera Administrative Region

2017₱2.4M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION (CONTINUATION) OF BASKETBALL COURT, PUCSUSAN, BAGUIO CITY, BENGUET

Baguio City DEO, Cordillera Administrative Region

2017₱2.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CONCRETE ROAD-CONCRETING OF ROAD AT KALAPATI ST. (PANGWI TO JUNCTION PINGET AND LOWER QUIRINO HILL BARANGAY RESIDENCE), BRGY. DIZON-MANZANILLO, BAGUIO CITY, BENGUET

Baguio City DEO, Cordillera Administrative Region

2019₱1.9M
Reported complete (DPWH)
View all 14 projects →

4. Implementation

Contract Amount

₱1,869,833.95

Progress

Reported complete (DPWH)

Start Date

February 16, 2016

Target End

April 19, 2016