Roads17PD0005

ASSET PRESERVATION OF NATIONAL ROADS- CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-TERTIARY:CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - QUEZON HILL RD. # 1, KO308+780-KO309+110

ASSET PRESERVATION OF NATIONAL ROADS- CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS-TERTIARY:CONSTRUCTION OF DRAINAGE STRUCTURE ALONG ROAD - QUEZON HILL RD. # 1, KO308+780-KO309+110 is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱2,617,806.19. Status: Reported complete (DPWH). Contractor on record: SEGAL CONST. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Sagudin River, Brookside, Baguio City, Benguet
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROX-17-0025803

₱6,505,000.00 · FY2017

Released to Northern Mindanao Medical Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

14 projects · ₱28.8M total · 0 flags

Other projects by this contractor

No sat.

LOCAL INFRASTRUCTURE PROGRAM-CONST OF MPB, BAGUIO CITY, BENGUET: A) CONST. OF MPB SAN ANTONIO AURORA HILL, BAGUIO CITY B) CONST. OF MPB , WEST BAYAN, LEONILA HILL, BAGUIO CITY

Baguio City DEO, Cordillera Administrative Region

2017₱4.4M
Reported complete (DPWH)
No sat.

CONTRACT PACKAGE 22: DRERF - FLOOD CONTROL AND DRAINAGE -DRAINAGE/PROTECTION WORKS: RESTORATION OF DAMAGE SLOPE PROTECTION DAMAGED BY TYPHOON OMPONG A) REVETMENT WALL ALONG BUED RIVER (F40033LZ) B) RESTORATION OF COLLAPSED REVETMENT WALL ALONG LOAKAN BR.1

Baguio City DEO, Cordillera Administrative Region

2018₱3.0M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM-OPENING AND CONCRETING OF ROAD BETWEEN BLOCK 1 AND 4 TAPAO PORTION OF THE BARANGAY, MIDDLE QUIRINO HILL, BAGUIO CITY, BENGUET

Baguio City DEO, Cordillera Administrative Region

2017₱2.4M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION (CONTINUATION) OF BASKETBALL COURT, PUCSUSAN, BAGUIO CITY, BENGUET

Baguio City DEO, Cordillera Administrative Region

2017₱2.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF CONCRETE ROAD-CONCRETING OF ROAD AT KALAPATI ST. (PANGWI TO JUNCTION PINGET AND LOWER QUIRINO HILL BARANGAY RESIDENCE), BRGY. DIZON-MANZANILLO, BAGUIO CITY, BENGUET

Baguio City DEO, Cordillera Administrative Region

2019₱1.9M
Reported complete (DPWH)
No sat.

LOCAL INFRASTRUCTURE PROGRAM-FLOOD CONTROL: CONSTRUCTION OF FLOOD CONTROL STRUCTURE (SLOPE PROTECTION) AT BROOKSIDE BARANGAY

Baguio City DEO, Cordillera Administrative Region

2016₱1.9M
Reported complete (DPWH)
View all 14 projects →

4. Implementation

Contract Amount

₱2,617,806.19

Progress

Reported complete (DPWH)

Start Date

May 28, 2017

Target End

August 13, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.