Bridges25I00152

BRIDGE - WIDENING OF PERMANENT BRIDGES - PUPUA PARALLEL BR. ALONG MAHALIKA HIGHWAY (SN ISIDRO - SN JUANICO BR.)

BRIDGE - WIDENING OF PERMANENT BRIDGES - PUPUA PARALLEL BR. ALONG MAHALIKA HIGHWAY (SN ISIDRO - SN JUANICO BR.) is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱33,722,192.69. Status: Past target date (DPWH On-Going). Contractor on record: RICHMARK CONST INC FOR:RICHMARK CONST. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

27 projects · ₱1.3B total · 0 flags

Other projects by this contractor

No sat.

ASSET PRESERVATION - REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROADS - RPIMARY ROADS - DAANG MAHARLIKA (SM) (SN ISIDRO - SN JUANICO BR) - K0810+500 - K0813+120, K0813+600 - K0814+500, K0816+000 - K0817+000, K0826+200 - K0827+000, SAMAR 2ND

Region VIII, Region VIII

2024₱197.9M
Past target date (DPWH On-Going)
No sat.

REHAB./RECONST./UPGRADING OF DAMGED PAVED ROADS - PRIMARY ROADS ALONG DAANG MAHARLIKA (SM) (SN ISIDRO-SN JUANICO BR), CATBALOGAN, PARANAS, HINABANGAN & CALBIGA, SAMAR

Samar 2nd DEO, Region VIII

2023₱107.3M
Reported complete (100% progress, DPWH status On-Going)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-ACCESS ROAD FROM BRGY. POLANGI-BRGY. PANAYURAN-BRGY. LITERON LEADING TO LULUGAYAN FALLS, CALBIGA RIVER AND ...... CALBIGA SAMAR

Region VIII, Region VIII

2021₱102.7M
Reported complete (DPWH)
No sat.

CONST. OF ROAD, BONGA - PAMAMAS-AN - LINOOBAN - MARARANGSI - CALUYAHAN, MOTIONG, SAMAR

Samar 2nd DEO, Region VIII

2022₱86.8M
Reported complete (DPWH)
No sat.

ASSET PRESERVATION - CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - PRIMARY ROADS - MAHARLIKA HIGHWAY (SN ISIDRO - SN JUANICO BR) K0722+200 - K0722+280, K0722+283 - K0722+503, K0723+000 - K0723+470, K0723+700 - K0723+930, K0725+0

Region VIII, Region VIII

2025₱63.0M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MODIFIED DESIGN WITH PARAPET, 4-STOREY, 20-CL SCHOOL BUILDING, TINGIB E/S, BASEY, SAMAR

Samar 2nd DEO, Region VIII

2019₱50.8M
Reported complete (DPWH)
View all 27 projects →

4. Implementation

Contract Amount

₱33,722,192.69

Progress

Past target date (DPWH On-Going)

Start Date

May 14, 2025

Target End

January 8, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.