Construction of Revetment22LA0121

Construction of Revetment along Pagtulian River, Sta. 0+000 - Sta. 0+750 (BS), Bukal, Nabunturan, Davao de Oro

Construction of Revetment along Pagtulian River, Sta. 0+000 - Sta. 0+750 (BS), Bukal, Nabunturan, Davao de Oro is a DPWH-tracked public work in NABUNTURAN (CAPITAL) (DAVAO DE ORO), DAVAO DE ORO, Region XI. Reported contract value: ₱57,215,519.61. Status: Reported complete (DPWH). Contractor on record: LEGACY CONST CORP FORMERLY: LEGACY CONST / DOUBLE J CONST AND SUPPLY. Figures trace to sumbong.

NABUNTURAN (CAPITAL) (DAVAO DE ORO), DAVAO DE ORO, Region XI
Region: Region XI

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱7,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Revetment of Flood Control, Purok 1, New Sibunga, Nabunturan, Davao de Oro
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003152

₱756,564,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002642

₱535,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002791

₱62,400,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002783

₱45,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0006775

₱37,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱57.2M total · 0 flags

4. Implementation

Contract Amount

₱57,215,519.61

Progress

Reported complete (DPWH)

Start Date

March 28, 2022

Target End

November 29, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.