Bridges20CJ0132

CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF BRIDGE ALONG SAN JOSE, TARLAC-PALAUIG, ZAMBALES ROAD, SAN JOSE, TARLAC

CONSTRUCTION / REPAIR / REHABILITATION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS CONSTRUCTION OF BRIDGE ALONG SAN JOSE, TARLAC-PALAUIG, ZAMBALES ROAD, SAN JOSE, TARLAC is a DPWH-tracked public work in Tarlac DEO, Region III. Reported contract value: ₱75,717,759.92. Status: Reported complete (DPWH). Contractor on record: HIGH STRENGTH DEV CORP. Figures trace to dpwh.

Tarlac DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Along San Isidro Creek, Tarlac City, Tarlac
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Tarlac DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

145 projects · ₱5.8B total · 2 flags

4. Implementation

Contract Amount

₱75,717,759.92

Progress

Reported complete (DPWH)

Start Date

November 24, 2020

Target End

July 6, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.