Buildings and Facilities19KC0101

CONSTRUCTION OF COVERED COURT PUROK KIHARE, TANKULAN, MANOLO FORTICH, BUKIDNON

CONSTRUCTION OF COVERED COURT PUROK KIHARE, TANKULAN, MANOLO FORTICH, BUKIDNON is a DPWH-tracked public work in Bukidnon 3rd DEO, Region X. Reported contract value: ₱2,475,000.00. Status: Reported complete (DPWH). Contractor on record: YMD BUILDERS AND CONST SUPPLY. Figures trace to dpwh.

Bukidnon 3rd DEO, Region X
Region: Region X

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROVI-19-0004088

₱270,000.00 · FY2019

Released to Burak National High School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,475,000.00

Progress

Reported complete (DPWH)

Start Date

September 20, 2019

Target End

December 18, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.