Roads22FG0075

CONST. OF ROAD, BRGY. PILI: STA.0+000.00-STA.0+424.00, BRGY. BULALACAO: STA.0+000.00-STA.0+217.00, BRGY. BITAOGAN: SECTION 1: STA.0+000.00-STA.0+156.00, SECTIOM 2: STA.0+000.00-STA.0+064.00, BRGY PILI, BULALACAO AND BITAOGAN, PRESENTACION, CAMARINES SUR

CONST. OF ROAD, BRGY. PILI: STA.0+000.00-STA.0+424.00, BRGY. BULALACAO: STA.0+000.00-STA.0+217.00, BRGY. BITAOGAN: SECTION 1: STA.0+000.00-STA.0+156.00, SECTIOM 2: STA.0+000.00-STA.0+064.00, BRGY PILI, BULALACAO AND BITAOGAN, PRESENTACION, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 4th DEO, Region V. Reported contract value: ₱9,326,356.25. Status: Reported complete (DPWH). Contractor on record: HRB CONST. Figures trace to dpwh.

Camarines Sur 4th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System of Mahaba Creek leading to Tambang River, Sitio Palayan, Brgy. Lamon, Goa, Camarines Sur
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Camarines Sur 4th DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱9,326,356.25

Progress

Reported complete (DPWH)

Start Date

April 5, 2022

Target End

May 31, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.