Flood Control and Drainage18IL0050

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS/CONSTRUCTION OF SUBANG DAKU FLOOD CONTROL, SUBA SECTION 2, STA. 5+160-5+817, SOGOD, SOUTHERN LEYTE (CONSTRUCTION OF FLOOD MITIGATION STRUCTURE), SOGOD, SOUTHERN LEYTE

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURE AND DRAINAGE SYSTEMS/CONSTRUCTION OF SUBANG DAKU FLOOD CONTROL, SUBA SECTION 2, STA. 5+160-5+817, SOGOD, SOUTHERN LEYTE (CONSTRUCTION OF FLOOD MITIGATION STRUCTURE), SOGOD, SOUTHERN LEYTE is a DPWH-tracked public work in Southern Leyte 1st DEO, Region VIII. Reported contract value: ₱23,617,624.58. Status: Reported complete (DPWH). Contractor on record: 888 ACY ENT. Figures trace to dpwh.

Southern Leyte 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱24,100,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Subang Daku Flood Control, Suba Section 2, Sta. 5+160 - 5+817, Sogod, Southern Leyte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0012182

₱40,000.00 · FY2018

Released to Regional Office - IVA (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

292 projects · ₱9.1B total · 5 flags

4. Implementation

Contract Amount

₱23,617,624.58

Progress

Reported complete (DPWH)

Start Date

February 1, 2018

Target End

October 23, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.