Bridges25A00039

RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES - BUGALLON BR. (B02143LZ) ALONG PANGASINAN - ZAMBALES RD (PHASE IV)

RETROFITTING / STRENGTHENING OF PERMANENT BRIDGES - BUGALLON BR. (B02143LZ) ALONG PANGASINAN - ZAMBALES RD (PHASE IV) is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱18,440,185.00. Status: Past target date (DPWH On-Going). Contractor on record: ALPHATEC CHEMICAL CORP. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

531 projects · ₱13.3B total · 0 flags

4. Implementation

Contract Amount

₱18,440,185.00

Progress

Past target date (DPWH On-Going)

Start Date

March 24, 2025

Target End

June 21, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.