Buildings and Facilities17JE0064

CONSTRUCTION OF ACTIVITY CENTER/COVERED COURT,BARANGAY DAO,PAGADIAN CITY, ZAMBOANGA DEL SUR

CONSTRUCTION OF ACTIVITY CENTER/COVERED COURT,BARANGAY DAO,PAGADIAN CITY, ZAMBOANGA DEL SUR is a DPWH-tracked public work in Zamboanga del Sur 1st DEO, Region IX. Reported contract value: ₱4,742,070.31. Status: Reported complete (DPWH). Contractor on record: MJMARI BUILDERS AND DEVELOPMENT CORP FORMERLY: MJMARI BUILDERS AND ENT. Figures trace to dpwh.

Zamboanga del Sur 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Salug Daku Flood Control, Brgy. Tumapic, Mahayag, Zamboanga Del Sur
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0006150

₱67,088.00 · FY2017

Released to Visayas State University (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

168 projects · ₱2.2B total · 2 flags

4. Implementation

Contract Amount

₱4,742,070.31

Progress

Reported complete (DPWH)

Start Date

July 26, 2017

Target End

September 23, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.