Buildings and Facilities19OG0014

REHABILITATION OF 3 STOREY, 12 CLASSROOM, BALARA ELEMENTARY SCHOOL, BRGY. PANSOL, QUEZON CITY

REHABILITATION OF 3 STOREY, 12 CLASSROOM, BALARA ELEMENTARY SCHOOL, BRGY. PANSOL, QUEZON CITY is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱4,696,404.00. Status: Reported complete (DPWH). Contractor on record: ONE EULUZ CONST CORP FORMERLY: EULUZ CONST. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

GAA FY2019 not yet loaded (source: DBM GAA)

2. Allotment

No SARO/NCA release rows linked to this project yet. See DBM release listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

25 projects · ₱182.0M total · 0 flags

Other projects by this contractor

No sat.

REHABILITATION OF MULTIPURPOSE BUILDING , BRGY. ACACIA, SILANG, CAVITE, CONSTRUCTION OF MULTIPURPOSE BUILDING , ZONE 1, BRGY. OLD BULIHAN, SILANG, CAVITE, CONSTRUCTION/ REHABILITATION OF BARANGAY HALL BUILDING , BRGY. LITLIT, SILANG, CAVITE, CONSTRUCTION

Region IV-A, Region IV-A

2018₱18.9M
Reported complete (DPWH)
No sat.

REHABILITATION OF MULTIPURPOSE BUILDING (COVERED COURT), BRGY. BALUBAD, SILANG, CAVITE, REHABILITATION OF MULTIPURPOSE BUILDING (COVERED COURT), BRGY. POOC L, SILANG, CAVITE, CONSTRUCTION OF MULTIPURPOSE BUILDING (COVERED COURT), ZONE 10, BRGY. BULIHAN, S

Region IV-A, Region IV-A

2018₱18.4M
Reported complete (DPWH)
No sat.

CONST OF FOUR (4) STOREY - EIGHT (8) CL SB @ PALANGUE 3, E/S, NAIC, CAVITE

Cavite 2nd DEO, Region IV-A

2017₱17.5M
Reported complete (DPWH)
No sat.

CONST OF THREE (3) STOREY SIX (6) CL SB @ PACHECO E/S, MAGALLANES, CAVITE

Cavite 2nd DEO, Region IV-A

2017₱14.2M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM LOCAL INFRASTRUCTURE PROGRAM LOCAL ROADS AND BRIDGES LOCAL ROADS CONCRETING OF ROAD, BRGY. PASONG LANGKA, SILANG, CAVITE, CONCRETING OF ROAD BRGY. DELAS ALAS, GENERAL MARIANO, ALVAREZ, CAVITE AND LOCAL PROGRAM CONSTRUCTION/ REPAIR/

Region IV-A, Region IV-A

2018₱14.1M
Reported complete (DPWH)
No sat.

LOCALLY FUNDED PROJECTS - LOCAL INFRASTRUCTURE PROGRAM (LIP) - ROADS AND BRIDGES - LOCAL BRIDGES AND LOCAL ROADS - COMPLETION OF FOOT BRIDGE, MALIA, GMA, CAVITE, CONCRETING OF ROAD, ADLAS, SILANG, CAVITE, CONCRETING OF ROAD, POBLACION I, GMA, CAVITE, CONC

Cavite 3rd DEO, Region IV-A

2017₱11.3M
Reported complete (DPWH)
View all 25 projects →

4. Implementation

Contract Amount

₱4,696,404.00

Progress

Reported complete (DPWH)

Start Date

June 17, 2019

Target End

January 12, 2020

5. Audit