Roads17MB0039

CONSTRUCTION/IMPROVEMENT OF JUNCTION PROVINCIAL ROAD TO BOLOMALA ELEMNTARY SCHOOL, STA. 0+000 - STA. 1+700, TUPI SOUTH COTABATO

CONSTRUCTION/IMPROVEMENT OF JUNCTION PROVINCIAL ROAD TO BOLOMALA ELEMNTARY SCHOOL, STA. 0+000 - STA. 1+700, TUPI SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 1st DEO, Region XII. Reported contract value: ₱16,655,691.93. Status: Reported complete (DPWH). Contractor on record: MJ TIONGSON CONST FORMERLY: MJT BUILDERS. Figures trace to dpwh.

South Cotabato 1st DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱42,881,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction/Rehabilitation of Flood Mitigation Facilities at Makar Bridge-I along Makar River, Sta. 0+000 - Sta. 0+518, General Santos City, South Cotabato
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0014366

₱181,800.00 · FY2017

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱16,655,691.93

Progress

Reported complete (DPWH)

Start Date

April 30, 2017

Target End

August 27, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.