GAA 2025 OO-125M00179

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - GENERAL SANTOS CITY-T'BOLI-SURALLAH RD - K1680 + 997 - K1681 + 030, K1681 + 050 - K1681 + 085, K1681 + 969 - K1682 + 014, K1681 + 986 - K1682 + 020, GENERAL SANTOS CITY

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - GENERAL SANTOS CITY-T'BOLI-SURALLAH RD - K1680 + 997 - K1681 + 030, K1681 + 050 - K1681 + 085, K1681 + 969 - K1682 + 014, K1681 + 986 - K1682 + 020, GENERAL SANTOS CITY is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱73,712,280.00. Status: Past target date (DPWH On-Going). Contractor on record: MJ TIONGSON CONST FORMERLY: MJT BUILDERS. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

25M00179

₱73,712,280.00 · REYDAN BUILDERS/ MJ TIONGSON CONSTRUCTION

Contractor

B

85 projects · ₱1.4B total · 0 flags

4. Implementation

Contract Amount

₱73,712,280.00

Progress

Past target date (DPWH On-Going)

Start Date

July 9, 2025

Target End

February 10, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.