Bridges23IG0069

CONSTRUCTION (COMPLETION) OF MAGANHAN BRIDGE ALONG BYPASS/DIVERSION ROAD, KILIM-SITIO TIPAY ROAD JUNCTION ORMOC-BAYBAY-SOUTHERN LEYTE BOUNDARY ROAD TO BUENAVISTA JUNCTION TO JUNCTION TAC-BAYBAY SOUTH ROAD, BAYBAY CITY, LEYTE

CONSTRUCTION (COMPLETION) OF MAGANHAN BRIDGE ALONG BYPASS/DIVERSION ROAD, KILIM-SITIO TIPAY ROAD JUNCTION ORMOC-BAYBAY-SOUTHERN LEYTE BOUNDARY ROAD TO BUENAVISTA JUNCTION TO JUNCTION TAC-BAYBAY SOUTH ROAD, BAYBAY CITY, LEYTE is a DPWH-tracked public work in Leyte 5th DEO, Region VIII. Reported contract value: ₱74,459,400.00. Status: Reported complete (DPWH). Contractor on record: LEDA CONST INC. Figures trace to dpwh.

Leyte 5th DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bartolini Flood Control Structure along Bartolini River, Brgy. Caridad, Baybay City, Leyte
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Leyte 5th DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

181 projects · ₱9.4B total · 0 flags

4. Implementation

Contract Amount

₱74,459,400.00

Progress

Reported complete (DPWH)

Start Date

May 31, 2023

Target End

February 18, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.