GAA 2025 OO-225I00046

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANGON RIVER (UPSTREAM), BARANGAY LIBERTAD, PALO, LEYTE

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANGON RIVER (UPSTREAM), BARANGAY LIBERTAD, PALO, LEYTE is a DPWH-tracked public work in Region VIII, Region VIII. Reported contract value: ₱191,290,027.95. Status: Past target date (DPWH On-Going). Contractor on record: LEDA CONST INC. Figures trace to dpwh.

Region VIII, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

181 projects · ₱9.4B total · 0 flags

Other projects by this contractor

No sat.

LOCALLY FUNDED PROJECTS, LOCAL INFRASTRUCTURE PROGRAM, ROADS AND BRIDGES, LOCAL ROADS, CONCRETING OF POBLACION (VALENCIA), ANOYON ROAD-OMJON ROAD 0.000 001, BOHOL

Region VII, Region VII

2017₱247.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BANGON RIVER (DOWNSTREAM), BARANGAY LIBERTAD, PALO, LEYTE

Region VIII, Region VIII

2025₱191.3M
Past target date (DPWH On-Going)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BY-PASSES/DIVERSION ROAD ALONG BRGY. KILIM - SITIO TIPAY ROAD JUNCTION ORMOC - BAYBAY - SOUTHERN LEYTE BOUNDARY ROAD TO B

Region VIII, Region VIII

2025₱163.8M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF LIBERTAD FLOOD CONTROL STRUCTURE ALONG BANGON RIVER, BARANGAY LIBERTAD, PALO, LEYTE

Region VIII, Region VIII

2024₱160.5M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MISSING GAPS CONNECTING NATIONAL ROADS, INCLUDING ROW ARTECHE, BRGY. CATUMSAN-JIPAPAD-LAS NAVAS-CATUBIG-RAWIS ROAD, INCLUDING BRIDGE, NORTHERN SAMAR 2ND LD, PACKAGE 2, NORTHERN SAMAR 2ND LD

Region VIII, Region VIII

2017₱158.1M
Reported complete (DPWH)
No sat.

SIPAG - ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES - CONSTRUCTION OF BY-PASSES/DIVERSION ROAD ALONG BRGY. KILIM - SITIO TIPAY ROAD JUNCTION ORMOC - BAYBAY - SOUTHERN LEYTE BOUNDARY ROAD TO B

Region VIII, Region VIII

2025₱148.3M
Past target date (DPWH On-Going)
View all 181 projects →

4. Implementation

Contract Amount

₱191,290,027.95

Progress

Past target date (DPWH On-Going)

Start Date

March 13, 2025

Target End

March 7, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.