Flood Control and Drainage25IC0015

CONSTRUCTION OF FLOOD CONTROL ALONG MALAIHAO CREEK, BARANGAY SAN ANTONIO POBLACION, ALANGALANG, LEYTE

CONSTRUCTION OF FLOOD CONTROL ALONG MALAIHAO CREEK, BARANGAY SAN ANTONIO POBLACION, ALANGALANG, LEYTE is a DPWH-tracked public work in Leyte 1st DEO, Region VIII. Reported contract value: ₱96,444,250.00. Status: Past target date (DPWH On-Going). Contractor on record: ONE MYRNA CONST AND SUPPLY. Figures trace to dpwh.

Leyte 1st DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱60,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Limbuhan River, Barangay Cantariwis, Tolosa, Leyte
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Leyte 1st DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

4. Implementation

Contract Amount

₱96,444,250.00

Progress

Past target date (DPWH On-Going)

Start Date

March 7, 2025

Target End

December 15, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.