Construction of Flood Mitigation Structure24HD0105

Construction of Flood Control and Drainage System along Taytayan Creek, Taytayan, City of Bogo, Cebu

Construction of Flood Control and Drainage System along Taytayan Creek, Taytayan, City of Bogo, Cebu is a DPWH-tracked public work in CITY OF BOGO (CEBU), CEBU, Region VII. Reported contract value: ₱49,000,000.00. Status: Reported complete (DPWH). Contractor on record: QM BUILDERS / ADAMANT DEVELOPMENT CORP. Figures trace to sumbong.

CITY OF BOGO (CEBU), CEBU, Region VII
Region: Region VII

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage System along Taytayan Creek, Taytayan, City of Bogo, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0010159

₱1,355,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0010161

₱125,000.00 · FY2024

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROVII-24-0006768

₱76,058.00 · FY2024

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

24HD0105

₱48,752,000.00 · ADAMANT DEVELOPMENT

Contractor

1 projects · ₱49.0M total · 0 flags

4. Implementation

Contract Amount

₱49,000,000.00

Progress

Reported complete (DPWH)

Start Date

July 24, 2024

Target End

February 9, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.