Flood Control and Drainage19ID0018

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITH MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF DAGUITAN-MARABONG RIVER FLOOD CONTROL,BRGY. BATUG,DULAG,LEYTE

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITH MAJOR RIVER BASINS AND PRINCIPAL RIVERS-CONSTRUCTION OF DAGUITAN-MARABONG RIVER FLOOD CONTROL,BRGY. BATUG,DULAG,LEYTE is a DPWH-tracked public work in Leyte 2nd DEO, Region VIII. Reported contract value: ₱41,467,007.11. Status: Reported complete (DPWH). Contractor on record: LANOY CONST. Figures trace to dpwh.

Leyte 2nd DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-19-0012417

₱167,533.00 · FY2019

Released to Leyte 2nd DEO (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱41,467,007.11

Progress

Reported complete (DPWH)

Start Date

June 7, 2019

Target End

December 24, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.