Flood Control and Drainage17EA0040

CONSTRUCTION OF CABUYO FLOOD CONTROL

CONSTRUCTION OF CABUYO FLOOD CONTROL is a DPWH-tracked public work in Marinduque DEO, Region IV-B. Reported contract value: ₱10,168,678.87. Status: Reported complete (DPWH). Contractor on record: M G SALAZAR CONST CORP FOR M G SALAZAR. Figures trace to dpwh.

Marinduque DEO, Region IV-B
Region: Region IV-B

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱10,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cabuyo Flood Control, Torrijos, Marinduque
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-17-0017531

₱2,981,000.00 · FY2017

Released to Regional Office - VI (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

222 projects · ₱9.0B total · 0 flags

Other projects by this contractor

View all 222 projects →

4. Implementation

Contract Amount

₱10,168,678.87

Progress

Reported complete (DPWH)

Start Date

March 13, 2017

Target End

February 9, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.