Construction of Flood Mitigation Structure21IM0052

Construction of Flood Mitigation Structure and Riverbank Protection, Greendale 1 and 3, Tacloban City, Leyte

Construction of Flood Mitigation Structure and Riverbank Protection, Greendale 1 and 3, Tacloban City, Leyte is a DPWH-tracked public work in LEYTE, Region VIII. Reported contract value: ₱33,609,332.12. Status: Reported complete (DPWH). Contractor on record: KAUIE BUILDERS & SUPPLIES INC FORMERLY: KAUIE BUILDERS AND CONST SUPPLIES. Figures trace to sumbong.

LEYTE, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Villa Diana, Tacloban City, Leyte
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010152

₱150,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010294

₱57,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010271

₱43,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0010168

₱20,000,000.00 · FY2021

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-21-0008980

₱20,000,000.00 · FY2021

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

15 projects · ₱423.4M total · 3 flags

4. Implementation

Contract Amount

₱33,609,332.12

Progress

Reported complete (DPWH)

Start Date

April 23, 2021

Target End

July 1, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.