Buildings and Facilities18HK0106

CONSTRUCTION OF FOUR (4) STOREY (2) ICT LAB AND 2-SCIENCE LAB AT MAYAPOSI HIGH SCHOOL (9.5MX23.00M), MABINAY, NEGROS ORIENTAL

CONSTRUCTION OF FOUR (4) STOREY (2) ICT LAB AND 2-SCIENCE LAB AT MAYAPOSI HIGH SCHOOL (9.5MX23.00M), MABINAY, NEGROS ORIENTAL is a DPWH-tracked public work in Negros Oriental 2nd DEO, Negros Island Region. Reported contract value: ₱17,316,120.34. Status: Reported complete (DPWH). Contractor on record: GONZALODO ENT. Figures trace to dpwh.

Negros Oriental 2nd DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Namangyan River Control, Mabinay, Negros Oriental
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-18-0030928

₱3,700,000.00 · FY2018

Released to Metro Manila Centers for Health Development (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

School Building

₱17,316,120.34 · GONZALODO ENTERPRISES

Contractor

B

297 projects · ₱8.5B total · 1 flags

4. Implementation

Contract Amount

₱17,316,120.34

Progress

Reported complete (DPWH)

Start Date

July 13, 2018

Target End

March 13, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.