Roads23BC0083

CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-SANCHEZ MIRA BAY VIEW BOULEVARD INCLUDING ACCESS ROAD LEADING TO BEACH RESORTS, SANCHEZ MIRA, CAGAYAN

CSSP-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-SANCHEZ MIRA BAY VIEW BOULEVARD INCLUDING ACCESS ROAD LEADING TO BEACH RESORTS, SANCHEZ MIRA, CAGAYAN is a DPWH-tracked public work in Cagayan 2nd DEO, Region II. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: KBL BUILDERS CONST. Figures trace to dpwh.

Cagayan 2nd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Nangoluan Flood Control Structure along Sanchez Mira River, Sanchez Mira, Cagayan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Cagayan 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

16 projects · ₱197.3M total · 0 flags

Other projects by this contractor

No sat.

CSSP- BASIC INFRASTRUCTURE PROGRAM (BIP)- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR / STRATEGIC PUBLIC BUILDINGS/ FACILITIES-CONSTRUCTION OF NAGSABARAN BRIDGE, BRGY. NAGSABARAN, CLAVERIA, CAGAYAN

Cagayan 2nd DEO, Region II

2022₱24.8M
Reported complete (DPWH)
No sat.

CONCRETING OF BRGY. LANGGAGAN-PATAGA-BACSAY FMR, SANCHEZ MIRA, CAGAYAN

Cagayan 2nd DEO, Region II

2021₱19.9M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM- BASIC INFRASTRUCTURE PROGRAM- ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONSTRUCTION OF ROAD, SANCHEZ MIRA, CAGAYAN

Cagayan 2nd DEO, Region II

2022₱19.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS: FLOOD MANAGEMENT PROGRAM: CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS-CONSTRUCTION OF CABICUNGAN FLOOD CONTROL PROJECT, C-4, CLAVERIA, CAGAYAN

Cagayan 2nd DEO, Region II

2021₱19.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF NATIONAL ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE-PRIMARY ROADS-MANILA NORTH RD- K0600+560-K0600+830, CLAVERIA, CAGAYAN

Cagayan 2nd DEO, Region II

2022₱14.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS (TOURISM ROAD INFRASTRUCTURE PROGRAM-TRIP)-CLAVERIA BAY VIEW BOULEVARD INCLUDING ACCESS ROAD, CLAVERIA, CAGAYAN

Cagayan 2nd DEO, Region II

2022₱14.6M
Reported complete (DPWH)
View all 16 projects →

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

March 20, 2023

Target End

June 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.