Buildings and Facilities17PL0148

CONSTRUCTION OF 1 STY 2 CL SB W/ ATTACHED CR BALAWAG ELEMENTARY SCHOOL, TABUK CITY, KALINGA

CONSTRUCTION OF 1 STY 2 CL SB W/ ATTACHED CR BALAWAG ELEMENTARY SCHOOL, TABUK CITY, KALINGA is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱3,421,703.42. Status: Reported complete (DPWH). Contractor on record: BMJ BUILDERS. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Ambato Flood Control, Kalinga
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROVIII-17-0008275

₱255,507.00 · FY2017

Released to Eastern Samar Al National Comprehensive High be School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

49 projects · ₱553.3M total · 0 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG CHICO RIVER AT DAMSITE

Lower Kalinga DEO, Cordillera Administrative Region

2025₱49.0M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM, BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES, CONSTRUCTION OF DPWH MOUNTAIN PROVINCE 2ND DEO SUPPORT FACILITIES (COMPLETION), SALIOK, NATONIN, MOUNTAIN PROVINCE

Mountain Province 2nd DEO, Cordillera Administrative Region

2023₱29.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF NGIPEN, BANTAY FLOOD CONTROL ALONG CHICO RIVER, BANTAY, TABUK CITY, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2019₱28.9M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION - REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS, SLOPE COLLAPSE, AND LANDSLIDE - SECONDARY ROADS - MT PROVINCE BDRY-CALANAN-PINUKPUK-ABBUT RD (CAGALUAN-CALAN

Lower Kalinga DEO, Cordillera Administrative Region

2024₱24.8M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF DPWH UPPER KALINGA DISTRICT ENGINEERING OFFICE BUILDING, KALINGA

Upper Kalinga DEO, Cordillera Administrative Region

2021₱24.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF LEVEL III WATER SUPPLY PROJECT, TANUDAN, KALINGA

Lower Kalinga DEO, Cordillera Administrative Region

2021₱24.4M
Reported complete (DPWH)
View all 49 projects →

4. Implementation

Contract Amount

₱3,421,703.42

Progress

Reported complete (DPWH)

Start Date

November 9, 2017

Target End

February 1, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.