Flood Control and Drainage23CL0023

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BAYTO RIVER (UPSTREAM NORTH APPROACH PHASE I), STA. CRUZ, ZAMBALES

CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, BAYTO RIVER (UPSTREAM NORTH APPROACH PHASE I), STA. CRUZ, ZAMBALES is a DPWH-tracked public work in Zambales 1st DEO, Region III. Reported contract value: ₱44,074,442.58. Status: Past target date (DPWH On-Going). Contractor on record: RAIK CONST AND DEVELOPMENT CORP FORMERLY: RAIK CONST AND SUPPLY. Figures trace to dpwh.

Zambales 1st DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 95%

UACS
18001
Amount
₱45,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure, Bayto River (Upstream North Approach Phase I), Sta. Cruz, Zambales
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zambales 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱44,074,442.58

Progress

Past target date (DPWH On-Going)

Start Date

February 21, 2023

Target End

October 18, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.