Roads24DM0021

NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT -SECONDARY ROADS - SN FRANCISCO - SN ANDRES - SN NARCISO RD -K0363+000 - K0363+700, SAN ANDRES, QUEZON

NETWORK DEVELOPMENT PROGRAM - OFF-CARRIAGEWAY IMPROVEMENT -SECONDARY ROADS - SN FRANCISCO - SN ANDRES - SN NARCISO RD -K0363+000 - K0363+700, SAN ANDRES, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱9,800,000.00. Status: Reported complete (DPWH). Contractor on record: ADAD ENGINEERING SERVICES. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Brgy. Cabuyao, Padre Burgos, Quezon
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Quezon 3rd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

55 projects · ₱871.1M total · 0 flags

4. Implementation

Contract Amount

₱9,800,000.00

Progress

Reported complete (DPWH)

Start Date

February 7, 2024

Target End

May 6, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.