REMOVAL OF EXISTING CONCRETE PAVEMENT: REPLACEMENT & CONSTRUCTION OF CONCRETE PAVEMENT FROM STA.KM.
REMOVAL OF EXISTING CONCRETE PAVEMENT: REPLACEMENT & CONSTRUCTION OF CONCRETE PAVEMENT FROM STA.KM. is a DPWH-tracked public work in Antique DEO, Region VI. Reported contract value: ₱14,848,891.22. Status: Reported complete (DPWH). Contractor on record: ST GERRARD CONST GEN CONTRACTOR. Figures trace to dpwh.
Satellite images processing — before/after tiles will appear here after the next batch run.
Total Contract Cost