CONST. OF BYPASS & DIVERSION ROADS, CDO DIVERSION ROAD EXT. (JCT. SAYRE HIGHWAY BALUBAL)-MANOLO FORT

CONST. OF BYPASS & DIVERSION ROADS, CDO DIVERSION ROAD EXT. (JCT. SAYRE HIGHWAY BALUBAL)-MANOLO FORT is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱54,972,015.53. Status: Reported complete (DPWH). Contractor on record: EQUI-PARCO CONST CO. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱54,972,015.53

Progress

Reported complete (DPWH)

Start Date

April 27, 2021

Target End

November 17, 2021

5. Audit