Construction of Flood Mitigation Structure23CD0121

Construction of Flood Control Structure, Santa Maria River and its tributaries (Bagbaguin-Bolacan), Bagbaguin, Santa Maria, Bulacan

Construction of Flood Control Structure, Santa Maria River and its tributaries (Bagbaguin-Bolacan), Bagbaguin, Santa Maria, Bulacan is a DPWH-tracked public work in SANTA MARIA (BULACAN), BULACAN, Region III. Reported contract value: ₱86,846,618.32. Status: Reported complete (DPWH). Contractor on record: M3 KONSTRACT CORP FORMERLY:MARGARITA CONST. Figures trace to sumbong.

SANTA MARIA (BULACAN), BULACAN, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure at Barangay Lalakhan, Santa Maria, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 2nd District Engineering Office · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

4. Implementation

Contract Amount

₱86,846,618.32

Progress

Reported complete (DPWH)

Start Date

April 24, 2023

Target End

March 31, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.