Flood Control and Drainage18KG0010

FLOOD MANAGEMENT PROGRAM - CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (PROJECT 1) ALONG BUTADON RIVER, (UPSTREAM (RS), STA. 0 + 000 - STA. 0+295), BRGY. BUTADON, KAPATAGAN, LANAO DEL NORTE.

FLOOD MANAGEMENT PROGRAM - CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE (PROJECT 1) ALONG BUTADON RIVER, (UPSTREAM (RS), STA. 0 + 000 - STA. 0+295), BRGY. BUTADON, KAPATAGAN, LANAO DEL NORTE. is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱46,478,186.82. Status: Reported complete (DPWH). Contractor on record: FFJJ CONST. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Money Trail

1. Appropriation

Probable match · score 89%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Project 1) along Butadon River, Upstream (RS), Brgy. Butadon, Kapatagan, Lanao Del Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-18-0014700

₱220,000,000.00 · FY2018

Released to Philippine Army ( rces ) Forces ) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱46,478,186.82

Progress

Reported complete (DPWH)

Start Date

April 18, 2018

Target End

November 7, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.