Construction of Revetment22DI0115

Construction of Revetment/Floodwall (Staggered), Biñan City, Laguna

Construction of Revetment/Floodwall (Staggered), Biñan City, Laguna is a DPWH-tracked public work in CITY OF BIÑAN (LAGUNA), LAGUNA, Region IV-A. Reported contract value: ₱34,278,213.80. Status: Reported complete (DPWH). Contractor on record: DATZLAV CONST. Figures trace to sumbong.

CITY OF BIÑAN (LAGUNA), LAGUNA, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Probable match · score 96%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Revetment/Floodwall (Staggered), Bi±an City, Laguna
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002907

₱1,026,969,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0003022

₱159,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-ROIVA-22-0007547

₱51,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002753

₱40,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

171 projects · ₱2.4B total · 0 flags

4. Implementation

Contract Amount

₱34,278,213.80

Progress

Reported complete (DPWH)

Start Date

July 11, 2022

Target End

February 26, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.