Flood Control and Drainage18OC0099

REHABILITATION OF CONCRETE REVETMENT WALL ALONG PARAÑAQUE MOUTH (PHASE V)PARAÑAQUE CITY, METRO MANILA

REHABILITATION OF CONCRETE REVETMENT WALL ALONG PARAÑAQUE MOUTH (PHASE V)PARAÑAQUE CITY, METRO MANILA is a DPWH-tracked public work in Metro Manila 2nd DEO, National Capital Region. Reported contract value: ₱46,065,067.94. Status: Reported complete (DPWH). Contractor on record: AKN CONST CORP. Figures trace to dpwh.

Metro Manila 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Concrete Revetment Wall along Parañaque Mouth (Phase V), Parañaque City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-BMB-E-18-0026815

₱450,000.00 · FY2018

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

129 projects · ₱8.0B total · 9 flags

4. Implementation

Contract Amount

₱46,065,067.94

Progress

Reported complete (DPWH)

Start Date

May 12, 2018

Target End

January 6, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.