Flood Control and Drainage21O00101

REHABILITATION OF PARANAQUE RIVER MOUTH (PHASE I AND PHASE II), BARANGAY DON GALO, PARANAQUE CITY

REHABILITATION OF PARANAQUE RIVER MOUTH (PHASE I AND PHASE II), BARANGAY DON GALO, PARANAQUE CITY is a DPWH-tracked public work in National Capital Region, National Capital Region. Reported contract value: ₱192,977,002.89. Status: Past target date (DPWH On-Going). Contractor on record: AKN CONST CORP. Figures trace to dpwh.

National Capital Region, National Capital Region
Region: National Capital Region

Follow the peso

2 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱185,908,058 · AKN CONST CORP

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    99% reported · imagery 2021-10-29 → 2025-04-25

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · NCR, Fourth District

Based on the coordinates published with the DPWH record and NOAH file Metro Manila.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: REHABILITATION OF PARANAQUE RIVER MOUTH (PHASE I AND PHASE II), BARANGAY DON GALO, PARANAQUE CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2021 GAA. DBM GAA FY2021

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

Confirmed (exact contract ID) · 100%

21O00101

₱185,908,058.41 · AKN CONST CORP

Award / contract ref: 21O00101

Contractor

B

128 projects · ₱7.9B total · 9 flags

4. Implementation

Contract Amount

₱192,977,002.89

Progress

Past target date (DPWH On-Going)

Start Date

November 26, 2021

Target End

September 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
National Capital Region (NCR)City of ParañaqueDon Galo
Storms whose wind field reached it
Fung-Wong 2025Fengshen 2025Man-Yi 2024Trami 2024Ewiniar 2024
Hazard exposure
Storm surgeDetails in Hazard context above.Full hazard check →
El Niño outlook (province)
No province on record.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.