Flood Control and Drainage20A00231

RECONSTRUCTION OF FLOOD CONTROL STRUCTURE ON ERODED BANK ALONG CURA RIVER (RIGHT BANK), BARANGAY SAGPATAN, DINGRAS, ILOCOS NORTE

RECONSTRUCTION OF FLOOD CONTROL STRUCTURE ON ERODED BANK ALONG CURA RIVER (RIGHT BANK), BARANGAY SAGPATAN, DINGRAS, ILOCOS NORTE is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱19,280,352.10. Status: Reported complete (DPWH). Contractor on record: A B TAYLAN CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2020 GAA. DBM GAA FY2020

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

98 projects · ₱4.4B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS, LAOAG-SAN NICOLAS BYPASS ROAD (LAOAG CITY-BACARRA SECTION), ILOCOS NORTE

Region I, Region I

2024₱238.8M
Past target date (DPWH On-Going)
No sat.

ROAD WIDENING - PRIMARY ROADS - MANILA NORTH ROAD - K0490+504-K0491+278; K0492+800-K0493+019; K0493+050-K0493+216; K0505+656-K0507+368; K0521+000-K0522+400; K0527+459-K0529+407; K0531+363-K0531+921; K0532+981-K0534+359

Region I, Region I

2018₱187.8M
Reported complete (DPWH)
No sat.

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS, IMPROVEMENT/CONCRETING OF PAOAY LAKE CIRCUMFERENTIAL ROAD AND MALACANANG TI AMIANAN, PAOAY, ILOCOS NORTE

Region I, Region I

2017₱178.5M
Reported complete (DPWH)
No sat.

CONSTRUCTION/ IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN) - PAOAY-LAOAG INTERNATIONAL AIRPORT ACCESS ROAD, PAOAY, ILOCOS NORTE

Region I, Region I

2025₱156.0M
Past target date (DPWH On-Going)
No sat.

IMPROVEMENT/WIDENING OF NATIONAL ROADS ALONG N1 (S00034LZ), MANILA NORTH ROAD, K0494 + 396 - K0495 + 024; K0496 + 164 - K0496 + 423; K0496 + 775 - K0497 + 444; K0497 + 834 - K0498 + 000; K0499 + 200 - K0500 + 676; K0500+676 - K0500 +698(L/S); K0500 +676 -

Region I, Region I

2016₱146.2M
Reported complete (DPWH)
No sat.

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO AIRPORTS (KALSADA TUNGO SA PALIPARAN, RILES AT DAUNGAN PROGRAM - KATUPARAN), PAOAY-LAOAG INTERNATIONAL AIRPORT ACCESS ROAD, PAOAY, ILOCOS NORTE

Region I, Region I

2024₱145.1M
Past target date (DPWH On-Going)
View all 98 projects →

4. Implementation

Contract Amount

₱19,280,352.10

Progress

Reported complete (DPWH)

Start Date

January 20, 2021

Target End

July 18, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.