Buildings and Facilities20BK0096

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (1 UNIT 2 STOREY BUILDING) BRGY. DON MARIANO PEREZ, DIFFUN, QUIRINO

CONSTRUCTION (COMPLETION) OF MULTI-PURPOSE BUILDING (1 UNIT 2 STOREY BUILDING) BRGY. DON MARIANO PEREZ, DIFFUN, QUIRINO is a DPWH-tracked public work in Quirino DEO, Region II. Reported contract value: ₱1,957,934.15. Status: Reported complete (DPWH). Contractor on record: JURIS CONST. Figures trace to dpwh.

Quirino DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 66%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Completion) of Multi-Purpose Building (1 unit 2 storey Building), Brgy. Don Mariano Perez, Diffun, Quirino
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Quirino DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

59 projects · ₱362.8M total · 0 flags

Other projects by this contractor

View all 59 projects →

4. Implementation

Contract Amount

₱1,957,934.15

Progress

Reported complete (DPWH)

Start Date

October 21, 2020

Target End

June 13, 2021

5. Audit