Bridges25J00099

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BRGY. ALVENDA, MUTIA - POB. SERGIO OSMEÑA SR. ROAD, ZAMBOANGA DEL NORTE

CONSTRUCTION OF BY-PASS AND DIVERSION ROADS - BRGY. ALVENDA, MUTIA - POB. SERGIO OSMEÑA SR. ROAD, ZAMBOANGA DEL NORTE is a DPWH-tracked public work in Region IX, Region IX. Reported contract value: ₱56,162,774.04. Status: Past target date (DPWH On-Going). Contractor on record: RUDHIL CONST. Figures trace to dpwh.

Region IX, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2025 GAA. DBM GAA FY2025

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

1,028 projects · ₱22.5B total · 0 flags

4. Implementation

Contract Amount

₱56,162,774.04

Progress

Past target date (DPWH On-Going)

Start Date

May 19, 2025

Target End

January 15, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.