Flood Control and Drainage17ND0043

CONSTRUCTION/RECHANNELING OF MAON CATCHMENT AREA-VILLA KANANGGA CREEK CALOT-BONBON CREEK WITH RCBC, BUTUAN CITY

CONSTRUCTION/RECHANNELING OF MAON CATCHMENT AREA-VILLA KANANGGA CREEK CALOT-BONBON CREEK WITH RCBC, BUTUAN CITY is a DPWH-tracked public work in Butuan City DEO, Region XIII. Reported contract value: ₱71,391,727.53. Status: Reported complete (DPWH). Contractor on record: GICAR CONST INC. Figures trace to dpwh.

Butuan City DEO, Region XIII
Region: Region XIII

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0019915

₱144,300.00 · FY2017

Released to University of Southeastern Philippines (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱71,391,727.53

Progress

Reported complete (DPWH)

Start Date

May 18, 2017

Target End

June 5, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.