Flood Control and Drainage24HG0009

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF LANGTAD, ARGAO FLOOD CONTROL (UPSTREAM), BARANGAY LANGTAD, ARGAO, CEBU

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF LANGTAD, ARGAO FLOOD CONTROL (UPSTREAM), BARANGAY LANGTAD, ARGAO, CEBU is a DPWH-tracked public work in Cebu 2nd DEO, Region VII. Reported contract value: ₱64,575,000.00. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: GICAR CONST INC. Figures trace to dpwh.

Cebu 2nd DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bulacao River Flood Control Structure, Talisay City, Cebu
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Cebu 2nd DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

4. Implementation

Contract Amount

₱64,575,000.00

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

March 19, 2024

Target End

November 3, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.