Bridges19K00250

CONSTRUCTION (COMPLETION) OF GATA BRIDGE II ALONG MARAWI-MASIU ROAD (POONA BAYABAO SECTION), K1592+368.75 - K1592+404.75, LANAO DEL SUR

CONSTRUCTION (COMPLETION) OF GATA BRIDGE II ALONG MARAWI-MASIU ROAD (POONA BAYABAO SECTION), K1592+368.75 - K1592+404.75, LANAO DEL SUR is a DPWH-tracked public work in Region X, Region X. Reported contract value: ₱9,371,969.98. Status: Reported complete (DPWH). Contractor on record: NJS CONST. Figures trace to dpwh.

Region X, Region X
Region: Region X

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱9,371,969.98

Progress

Reported complete (DPWH)

Start Date

August 19, 2019

Target End

March 20, 2020

5. Audit